Why US Energy Companies Are Moving Into Data Centre Development
US energy companies are entering data centre development to capitalise on rising AI-driven electricity demand. By investing in dedicated power generation, natural gas infrastructure and powered-land campuses, they are addressing grid constraints while securing long-term partnerships with hyperscalers and data centre developers.
Key Takeaways
- US data-centre electricity use could rise about 3.4 times between 2024 and 2030, from 192 TWh to 649 TWh (LBNL reference case). EPRI puts data centres at 9% to 17% of US electricity by 2030, up from about 4.5% today.
- The main constraint on new campuses has moved from land to energised megawatts. Berkeley Lab finds the median grid project now takes more than five years from interconnection request to commercial operation.
- Power companies are entering data-centre development at four levels, from long-term supplier to campus co-developer.
- The four 2026 projects examined here plan about 11.4 GW of new generation, almost all of it gas-fired, plus 2.6 GW of battery storage.
- Blackridge counts 378 GW of US gas power in development, but only 52 GW under construction. The IEA expects just 15 to 27 GW of onsite gas for data centres worldwide by 2030. Most of the pipeline will not be built, and the companies that energise first are likely to win.
Power companies are moving into data-centre development because reliable, on-time electricity has become the scarcest input for AI and cloud campuses. Lawrence Berkeley National Laboratory (LBNL) projects US data-centre electricity use rising from 192 TWh in 2024 to 649 TWh in 2030, or 11.8% of national demand, and the International Energy Agency (IEA) expects data centres to account for about half of all US electricity demand growth to 2030.
For most of the past two decades, the hardest part of building a data centre was finding the right land at the right price, close to fibre and customers. That is no longer true. In 2026 the question that decides whether a campus gets built, and how fast, is simpler: can you energise it?
That shift explains one of the most striking trends in US infrastructure this year. Oil majors, independent power producers and energy services companies have announced deals that put them at the heart of data-centre development.
This article explains why US energy companies are entering data centre development, the factors driving this shift, and how they are positioning themselves to capitalise on growing AI-driven electricity demand.
US Data Centre Electricity Demand Could More Than Triple by 2030
The scale of US data centre electricity demand is becoming a major concern for the country's power sector. According to the Lawrence Berkeley National Laboratory's (LBNL) June 2026 United States Data Center Energy Usage Report, prepared for the US Department of Energy (DOE), data centres consumed an estimated 192 TWh of electricity in 2024, representing 4.7% of total US electricity consumption.
Under LBNL's reference scenario, consumption could reach 649 TWh by 2030, increasing data centres' share of national electricity use to 11.8%.
Scenario | US data centre electricity consumption | Share of US electricity | Multiple of 2024 consumption |
|---|---|---|---|
2024 estimate | 192 TWh | 4.70% | 1.0× |
2030 low case | 521 TWh | 9.50% | 2.7× |
2030 reference case | 649 TWh | 11.80% | 3.4× |
2030 high case | 843 TWh | 15.30% | 4.4× |
Source: LBNL, June 2026. Multiples calculated by Blackridge Research.
What We Found: 52 GW of Additional Average Power Demand
Blackridge Research's analysis of LBNL's projections highlights the scale of additional electricity supply required to support US data centre expansion.
22.5% annual growth: LBNL's reference scenario implies a compound annual growth rate (CAGR) of approximately 22.5% in data centre electricity consumption between 2024 and 2030.
52 GW of additional average load: Converting annual electricity consumption into average power demand, US data centres would increase from approximately 22 GW in 2024 to 74 GW in 2030.
3.4 times higher consumption: By 2030, data centres could consume more than three times their 2024 electricity use under LBNL's reference scenario.
These estimates represent average electricity demand, not installed generation capacity. Actual power requirements will also depend on peak loads, backup arrangements, reserve margins and the availability of electricity throughout the day.
The challenge is that this growth is arriving after a prolonged period of relatively slow electricity demand expansion. According to the US Energy Information Administration (EIA), national electricity demand grew by approximately 0.1% annually between 2005 and 2019, before accelerating to around 1.7% annually from 2020 to 2025.
The EIA's February 2026 Short-Term Energy Outlook projects electricity demand growth of 1.9% in 2026 and 2.5% in 2027. Regional demand is rising faster in markets with significant data centre development. ERCOT (Texas) is expected to record approximately 10% annual growth, while PJM is projected to grow by around 3%.
Why Rising Data Centre Demand Is Creating Opportunities for US Energy Companies
Rising data centre electricity demand is an opportunity for US energy companies. As AI and cloud infrastructure expand, developers need access to large volumes of reliable electricity, dedicated generation capacity and supporting energy infrastructure.
Securing grid connections and bringing sufficient power online within project timelines is the major challenge. Companies with existing power generation assets, natural gas supplies, transmission infrastructure and grid expertise can work directly with data centre developers to secure long-term power supply and accelerate project delivery.
This is changing the role of energy companies in the data centre market. Rather than operating solely as electricity suppliers, they are increasingly becoming development partners, investing in dedicated power plants, co-located generation facilities and integrated energy infrastructure. This allows them to capture value from both electricity generation and the growing demand for AI and cloud computing infrastructure.
The Real Bottleneck in US Data Centre Development Is Time, Not Land
Rising electricity demand is only part of the reason energy companies are entering data centre development. The bigger challenge is securing reliable power and bringing new generation capacity online quickly enough to meet project timelines. Grid interconnection delays, equipment shortages and fuel price volatility are making traditional power procurement increasingly difficult.
Grid Interconnection Delays Are Slowing Development
The median generation project in the US takes more than five years to move from an interconnection request to commercial operation as per Berkeley Lab’s report. Only 13% of generation capacity entering interconnection queues between 2000 and 2020 became operational by the end of 2025, while 75% withdrew.
Meanwhile, proposed natural gas generation capacity in interconnection queues increased by 86% in one year to 253 GW. This reflects growing interest in dispatchable power as developers seek alternatives to delayed grid connections.
Power Supply and Equipment Constraints Are Increasing
Several US electricity markets, including MISO, PJM and ERCOT, face elevated risks of insufficient reserve margins over the next five years as demand grows faster than new generation capacity.
Equipment availability adds to the challenge. Gas turbine orders increased by 70% in 2025, while leading manufacturers face multi-year delivery timelines. The EIA expects 86 GW of new US generating capacity in 2026, but only 6.3 GW is expected from natural gas.
Energy Companies Have a Speed-to-Power Advantage
Energy companies already control assets that can accelerate data centre development, including power plants, natural gas supplies, pipelines, substations and generation sites. Their experience in permitting and building energy infrastructure also gives them an advantage.
This is driving a shift towards a power-first development model. Instead of selecting land first and waiting for utility connections, developers are increasingly planning data centre campuses around available or dedicated generation capacity.
Co-located power plants still require permits, fuel contracts, equipment and construction. However, they offer an alternative to congested grid queues while giving energy companies long-term customers and direct investment opportunities in digital infrastructure.
Four Ways Power Companies Are Entering the Data-Centre Market
Not every power company is becoming a data-centre landlord. The 2026 deals show four distinct levels of involvement, which Blackridge calls a participation ladder. Each step up brings the power company closer to the campus itself, with more upside and more risk.
| Model | What the power company does | 2026 example |
|---|---|---|---|
1 | Long-term power supplier | Builds dedicated generation and sells output to one data-centre customer | Chevron, Project Kilby |
2 | Powered-land joint venture | Supplies generation and energy management inside a campus JV | Liberty Energy and PowerBridge, Alpha Digital |
3 | Energy campus beside a digital campus | Builds and runs a large generation campus next to a separate data-centre campus | NextEra and Related, Project Star |
4 | Campus coalition partner | Owns dedicated generation within a jointly developed data-centre campus | NextEra and Brookfield, Paducah |
Rung 1: Long-term power supplier: Chevron's Project Kilby
In June 2026, Chevron signed a 20-year power purchase agreement with Microsoft for Project Kilby, a planned 2.67 GW gas-fired power facility in West Texas co-located with a Microsoft-operated data center. Chevron, through Energy Forge One and with development support from Engine No. 1, will build the plant using GE Vernova turbines plus units from Caterpillar's Solar Turbines, fuelled by Permian gas. First power is expected in 2028, with a final investment decision expected by the end of 2026.
Chevron is not building or running the data centre. It is doing what an oil and gas major does best, turning its own gas into a long-term contracted revenue stream, but with a 20-year technology customer instead of the commodity market. For Microsoft, the deal buys dedicated, dispatchable power on a timetable the grid could not guarantee.
Rung 2: Powered-land joint venture: Liberty Energy and PowerBridge
In July 2026, oilfield services company Liberty Energy and PowerBridge formed a joint venture to support Alpha Digital, a planned 2 GW powered data-centre campus in West Texas. PowerBridge contributes the campus development platform, while Liberty Power Innovations supplies power generation and energy management. The first phase is expected to include more than 300 MW of generation, with first power in Q4 2027 and deployment continuing through H1 2028.
This is the "powered land" model: the partners sell data-centre developers a site that comes with electricity already planned, rather than an empty plot waiting for a grid connection. Liberty is not the data-centre operator. It is using its experience running mobile power for oilfield operations to enter a new market.
Rung 3: Energy campus beside a digital campus: Project Star
Announced in September 2026 with the US Department of Commerce and the Republic of Korea, Project Star is a USD 22.3 billion energy infrastructure campus near Encinal, Texas. NextEra Energy Resources and Related Companies plan to develop, build and run 6.47 GW of natural gas generation, with Lewis Energy Group supplying gas infrastructure. Next door, Related Digital is developing a 5 GW digital infrastructure campus.
Project Star shows how large the energy side of a data-centre project can become. Here the energy campus is a separately identified investment of more than USD 22 billion, and its planned generation (6.47 GW) exceeds the capacity of the digital campus it supports (5 GW). The two figures measure different things and should not be added together.
Rung 4: Campus coalition partner: Paducah American Energy Hub
In July 2026, the Department of Energy announced a partnership to redevelop its former uranium enrichment site in Paducah, Kentucky, into the Paducah American Energy Hub. The USD 100 billion privately funded project is led by a coalition including Brookfield, with NextEra selected to develop and own the dedicated energy resources.
Plans include up to 2 GW of natural gas generation and up to 2.6 GW of battery storage, supporting up to 1.8 GW of utility capacity and more than 1.2 GW of compute. Full construction is targeted for 2032, subject to definitive agreements.
Paducah is the highest rung on the ladder: the energy developer is part of a coalition shaping the whole campus, on federal land, with dedicated generation and storage planned from the start. It also shows the government using surplus federal sites to attract AI infrastructure.
Five Key Patterns Emerging From US Energy and Data Centre Deals
1. Natural Gas Is the Preferred Power Source
At least three of the four projects rely on natural gas. Project Kilby plans approximately 2.67 GW, Project Star 6.47 GW and Paducah up to 2 GW, supported by 2.6 GW of battery storage. Alpha Digital's first phase also includes more than 300 MW of generation capacity. Together, the four projects represent approximately 11.4 GW of planned generation.
This reflects the broader US energy market. Natural gas supplied approximately 40% of US electricity in 2025, according to the EIA. Blackridge Research's database tracks 378 GW of US natural gas power capacity in development as of August 2026, up 50% from 252 GW in January. Texas alone accounts for 77 GW of planned gas capacity intended to directly power data centres.
Natural gas plants and engines offer dispatchable electricity and can support continuous operations, making them suitable for large AI and hyperscale campuses.
2. Power Generation Capacity Matches or Exceeds Campus Requirements
Energy companies are planning generation capacity at or above the requirements of their associated data centre campuses. At Project Star, 6.47 GW of planned generation exceeds the adjacent 5 GW digital campus capacity by approximately 29%.
At Paducah, up to 2 GW of gas generation and 2.6 GW of battery storage provide a combined 4.6 GW of planned energy capacity. This supports up to 1.8 GW of utility capacity and more than 1.2 GW of computing infrastructure.
These arrangements provide additional capacity for peak demand, maintenance and operational redundancy. They also reflect the importance of reliable power supply for AI workloads.
3. Texas and Federal Sites Are Emerging as Key Development Locations
Three of the four projects are located in Texas, where natural gas availability, large development sites and ERCOT's independent grid create opportunities for dedicated power and data centre campuses.
Blackridge Research's database tracks 122 GW of natural gas power capacity in development across Texas, representing nearly one-third of the US pipeline. The EIA also expects ERCOT electricity demand to grow by approximately 10% annually in 2026 and 2027.
The fourth project, Paducah, reuses a former Department of Energy site in Kentucky. Project Star also involves collaboration with the US Department of Commerce and the Republic of Korea. These developments highlight the growing role of government-backed sites, partnerships and investment in large-scale digital infrastructure.
4. Long-Term Power Contracts Support Project Financing
Long-term electricity agreements are helping energy companies justify investments in dedicated generation. Chevron's 20-year agreement with Microsoft is a key example. A long-term commitment from a major data centre customer provides greater revenue visibility and reduces exposure to fluctuations in wholesale electricity prices.
This is particularly important as the Energy Institute reported that US natural gas prices increased by approximately 50% in 2025. Securing long-term customers and fuel supply arrangements can improve the financial viability of new power projects.
5. Project Delivery Is Concentrated Between 2027 and 2032
Despite dedicated generation, these developments require several years to reach operation. Alpha Digital expects first power in Q4 2027, while Project Kilby targets 2028. Paducah is targeting full construction completion by 2032.
Equipment procurement and permitting remain important constraints. Gas turbine orders increased by 70% in 2025, according to the IEA, while the EIA expects only 6.3 GW of new natural gas generation capacity to become operational across the US in 2026.
Projects that secure turbines, fuel supply, permits and construction resources early will be better positioned to meet their delivery schedules.
Conclusion: Power Access Will Shape the Next Phase of US Data Centre Development
The entry of US energy companies into data centre development reflects a fundamental shift in the infrastructure market. As AI and cloud computing increase electricity demand, access to reliable power is becoming as important as land, connectivity and capital.
For data centre developers, this means prioritising partnerships with companies that control generation capacity, fuel supplies and grid infrastructure. For utilities and independent power producers, long-term data centre agreements offer opportunities to finance new generation, although customer concentration and project delays remain risks.
Oil and gas companies can also expand beyond traditional fuel supply by investing in dedicated power generation and serving technology companies through long-term electricity contracts.
For investors, contractors and equipment suppliers, the key indicators to watch are final investment decisions, signed power agreements, turbine and transformer orders, permitting progress and construction starts.
Frequently Asked Questions
Why are US energy companies investing in data centre development?
US energy companies are investing in data centres to meet rising electricity demand, supply dedicated power and secure long-term contracts with technology companies.
How much electricity will US data centres use by 2030?
US data centres could consume 649 TWh of electricity by 2030, accounting for 11.8% of national electricity consumption, according to LBNL's reference scenario.
Are utilities building data centres themselves?
Most utilities and power companies are partnering with data centre developers or supplying dedicated generation rather than operating data centres themselves.
What is a powered-land data centre campus?
A powered-land data centre campus is a development site with planned or existing electricity supply and infrastructure to support data centre operations.
Why are data centres turning to onsite natural gas generation?
Onsite natural gas generation provides reliable, continuous electricity and reduces dependence on delayed grid connections and transmission upgrades.
Which US energy companies are entering data centre development?
Companies such as Chevron and NextEra Energy are investing in power generation and infrastructure to support large-scale US data centre developments.