ERCOT vs PJM: Which Electricity Market Is Better for Data Center Developers in 2026?

Compare ERCOT and PJM electricity markets for data center developers in 2026. Explore power availability, electricity pricing, grid capacity, transmission infrastructure, and investment opportunities to identify which market offers better conditions for data center development in the United States.

MV
Madhuri Vuggina
Nov 20, 2026/19 min read
ERCOT vs PJM: Which Electricity Market Is Better for Data Center Developers in 2026?

Key Takeaways

  • ERCOT and PJM offer different benefits for data center development. ERCOT is a competitive energy-only market, whereas PJM has both energy and centralized capacity markets.
  • Access to power is a critical site-selection factor. Before choosing a location, developers need to evaluate the generation capacity, transmission infrastructure, grid congestion, and utility hookup needs.
  • A lot of large-load demand is coming to ERCOT. ERCOT stated in June 2026 that it was tracking more than 438,000 MW of large-load requests, with nearly 89% of those requests coming from data centers.
  • Growing capacity problems are affecting PJM. Its July 2026 capacity auction found a predicted shortfall of 6.8 GW versus its reliability need for the 2028/2029 delivery year.
  • Electricity prices vary between the two markets. Under ERCOT, purchasers face energy-price instability, while PJM adds capacity-market fees to energy and transmission rates.
  • Another big distinction is grid connectivity. Unlike PJM, which connects to the larger Eastern Interconnection, ERCOT's grid remains mostly isolated and has only a few DC interconnections.
  • Interconnection timelines and infrastructure upgrades can affect project feasibility. Developers should get site-specific estimates of utility capacity, transmission needs and interconnection timing.
  • A better market depends on project needs. PJM has developed data center hubs and a larger integrated grid, but ERCOT may appeal to developers who prefer Texas sites and flexible power procurement.

Introduction:


According to E&E News, ERCOT's performance in mid-July was notable: the system set a record, but there were no emergencies and prices did not rise as they did in PJM earlier in the month.

The outlet says that the difference is mostly due to the mix of resources. In contrast to PJM and SPP, ERCOT has "a lot of solar and batteries." E&E News reports that at 6 p.m. on July 22, ERCOT's peak, solar power produced about a third of the power, and prices were about $29 per megawatt-hour.

It looked like PJM's peak experience was different. E&E News says that around July 2, PJM saw prices rise above $2,000 per megawatt-hour. PJM also said that demand would have broken a record set 20 years ago if conservation programs that lowered load during the busiest hours had not been in place.

That gap is the standard for an operator. It means that the "cost of tightness" can be orders of magnitude higher in markets with more evening peak exposure. It also shows how quickly voluntary load reduction can become a tool for improving reliability. If data center managers can move compute tasks that aren't needed right away, pre-cool thermal storage, or use batteries behind the meter, those programs can save them a lot of money, but only if they're contractually available and can be sent out when the grid calls.


What Are ERCOT and PJM?


To compare ERCOT and PJM, you should first know how these two electricity markets work.

ERCOT electricity market (Electric Reliability Council of Texas)

ERCOT is in charge of the electricity grid that serves about 90% of Texas's electric load. It runs a competitive wholesale energy market and makes sure that supply and demand are balanced across its network of interconnected power plants.

ERCOT works mostly on its own, not connected to the interstate transmission networks like most other regional transmission organizations in the US. The structure of its electricity market is different from PJM's because it doesn't link to as many neighboring grids. ERCOT's electricity grid is mostly isolated and doesn't have much direct current (DC) to nearby power systems. This means that it can't bring in electricity when demand is high or when there are supply problems. In contrast to PJM, the Public Utility Commission of Texas (PUCT) oversees ERCOT's wholesale electricity market at the state level. The federal government has a different regulatory framework for ERCOT because it has fewer interstate grid connections. For people who are building data centers, this means carefully looking at things like the area's power generation, transmission, and interconnection needs, as well as the need for backup power on-site to make sure there is a steady supply of energy, especially for big AI and hyperscale facilities.

Texas has become a popular place for hyperscale data centers and AI infrastructure because it has a lot of land available, more generation resources, the possibility for renewable energy, and a competitive electricity market.

But growing demand from big electricity users has put a lot of stress on the grid's infrastructure.

In June 2026, the Public Utility Commission of Texas gave its approval to ERCOT's Batch Zero process for requests to connect large amounts of power (75 MW or more). More than 438,000 MW of large-load requests were sent to ERCOT and data centers accounted for almost 89% of these requests. These are requests that have not been accepted or committed to.An announcement from ERCOT on June 18, 2026, said that the organization was keeping of more than 438,000 MW (438 GW) of requests for large-load interconnection, with data centers making up almost 89% of those requests. These numbers show suggested connections; they do not show approved or actual power capacities.


PJM electricity market (PJM Interconnection)

PJM Interconnection is a regional transmission organization (RTO) that works with 13 states and Washington, D.C. to coordinate wholesale electricity markets and transmission operations.

Northern Virginia, Ohio, Pennsylvania, New Jersey, Maryland, and Illinois are just a few of the big data center areas that it serves. PJM is a key part of meeting the electricity needs of hyperscale cloud providers, colocation operators, and enterprise data centers.

The area has a well-established transmission network and access to a wide range of power sources, such as natural gas, nuclear power, coal, wind power, and solar power. That being said, AI data centers and other big industrial facilities are using more electricity, which is making it harder to plan the grid and connect to other networks.

Is ERCOT like PJM?

No, both ERCOT and PJM are independent system operators (ISOs), but they work with different rules and structures for the energy market.

ERCOT is in charge of most of Texas's power grid. It's a mostly island system with only a few direct-current (DC) links to other grids in the area. It mostly uses an energy-only wholesale market, which means that generators make most of their money from selling electricity and other services, not from a central capacity auction.

PJM, on the other hand, runs a cable system in the Eastern Interconnection that connects 13 states and Washington, D.C. It runs both wholesale energy markets and the Reliability Pricing Model (RPM), which is a centralized capacity market.

ERCOT vs PJM: Market Comparison at a Glance

When developers look at these electricity markets, the following table shows the main changes they should know about.

Comparison Factor

ERCOT

PJM

Full Name

Electric Reliability Council of Texas

PJM Interconnection

Market Classification

Independent System Operator (ISO)

Regional Transmission Organization (RTO)

Geographic Coverage

Most of Texas

13 states and Washington, D.C.

Electricity Market Structure

Competitive wholesale energy market

Wholesale energy and capacity markets

Grid Structure

Largely independent Texas electricity grid

Interconnected regional transmission network

Major Data Center Markets

Dallas-Fort Worth, Austin, Houston, and

San Antonio

Northern Virginia, Columbus, Pennsylvania,

and New Jersey

Electricity Generation

Natural gas, wind, solar, nuclear, and storage

Natural gas, nuclear, coal, hydro, wind, and

solar

Capacity Market

No traditional centralized capacity market

Operates a centralized capacity market

Large-Load Integration

Batch Zero and associated large-load

procedures

PJM and utility-led large-load service and

transmission processes

Power Procurement

Retail electricity providers, bilateral contracts,

and PPAs

Utilities, retail suppliers, wholesale markets,

and bilateral agreements

Major Advantage

Competitive electricity market and expanding

energy resources

Established transmission network and major

data center ecosystem

Major Challenge

Rapid demand growth and transmission

constraints

Capacity costs, congestion, and

interconnection challenges

Renewable Energy Opportunities

Significant wind and solar development

Nuclear, wind, solar, and other renewable

resources

Key Development Consideration

Confirm deliverable power and transmission

requirements.

Confirm utility service, capacity arrangements

, and transmission availability.

Differentiating between the two markets is important for data center builders because buying electricity, planning for reliability, getting access to transmission, and project costs are all very different.

What Is the ERCOT Power Forecast for the Future?

Data centers, AI infrastructure, industrial growth, and other big electricity users are expected to make Texas's electricity demand go up a lot over the next few years, according to ERCOT.

ERCOT's preliminary Long-Term Load Forecast, released on April 15, 2026, projected approximately 367,790 MW of peak demand by 2032 when transmission and distribution providers' reported large- and medium-load requests were included. However, ERCOT's underlying forecast for the same year was 111,318 MW. The difference reflects the scale of prospective electricity demand submitted by developers and other large consumers, not confirmed projects or guaranteed future consumption. ERCOT identified the higher scenario as preliminary and subject to further review and refinement.

But there is a big catch to this number: it was just a rough guess based on requests. It doesn't mean that all of the planned projects will be built or connected. After that, ERCOT asked for changes to be made to take into account past project completion rates, supply chain problems, and how likely it was that proposed loads would come true.

What Is the PJM Power Forecast for the Future?


According to PJM Interconnection, the need for electricity will rise a lot over the next 20 years. This will mostly be due to the growth of data centers, artificial intelligence (AI), manufacturing, electric vehicles, and buildings that are wired for electricity.

PJM's January 2026 Long-Term Load Forecast says that over the next 10 years, summer peak electricity demand will rise by an average of 3.6% per year, hitting about 222,106 MW (222.1 GW) by 2036 and 253,077 MW (253.1 GW) by 2046. Also, peak demand in the winter is expected to go up, reaching about 204,650 MW by 2035/2036. 

Data centers are a big part of this growth, which puts more stress on the grid's ability to generate power, transmit power, and be reliable. PJM will need more production resources, better transmission upgrades, energy storage, and better large-load planning to meet future demand. These predictions show data center builders how important it is to make sure they have a steady supply of electricity and can connect to the grid before starting new projects.


ERCOT vs PJM electricity pricing for data centers

Power is one of the most expensive costs for hyperscale and AI data centers. All year long, facilities with 50 MW, 100 MW, or more need a lot of electricity.

Any change in the price of electricity per kilowatt-hour can significantly affect long-term business costs.

Electricity Pricing in ERCOT

ERCOT runs a wholesale market for energy-only electricity. Generators make most of their money from selling power and other services, not from a traditional centralized capacity market.

As a result of this structure, data center developers can look into competitive power supply deals and different ways to buy power.

Texas also has a lot of wind and solar power resources, which makes it possible to buy renewable energy and make long-term power purchase agreements (PPAs).

But energy prices can change a lot when there is bad weather, a lot of demand, and not enough generation available.

Developers should evaluate: 

  • Changes in the price of wholesale electricity.

  • Agreements for selling power to consumers.

  • Fees for transmission and distribution.

  • Peak usage and demand charges.

  • Options for buying renewable energy.

  • Needs for battery storage and backup generation.


Electricity Pricing in PJM

PJM runs both the wholesale energy market and the capacity market. Its capacity market is meant to make sure that there are enough power plants to meet future demand. Operators of data centers have to think about how much it costs to get electricity, how much it costs to send data, and what the local utility rates are.

Rising demand from hyperscale data centers has made people in the region more worried about future capacity needs and the cost of electricity. The real cost of electricity for developers relies on where the project is located, the utility's service area, capacity requirements, traffic, and any supply agreements that have been made.


ERCOT vs PJM Electricity Pricing Comparison

Pricing Component

ERCOT

PJM

Wholesale Energy Pricing

Competitive market-based pricing

Competitive market-based pricing

Capacity Market Costs

No traditional centralized capacity market

Centralized capacity market

Electricity Price Volatility

Can experience significant price fluctuations

Varies by location, congestion, and market

conditions

Retail Supply Options

Competitive retail market in many areas

Depends on state regulations and utility

territory

Renewable Energy Contracts

Wind and solar PPAs

Nuclear and renewable energy procurement

options

Long-Term Cost Planning

Requires careful management of market exposure

Requires consideration of energy and capacity

costs


Which market offers lower electricity costs?


There isn't a single answer. In some places, ERCOT may offer good buying opportunities. On the other hand, PJM's economics depend a lot on the costs of capacity, transmission, and electricity supply. Instead of using market-wide averages, developers should look at how much electricity costs for each project.

These observations should not be interpreted as a direct comparison of average electricity costs between the two markets. Wholesale prices vary by location, time of day, congestion and system conditions. ERCOT's lower price at the cited peak hour also illustrates the contribution of solar generation and battery storage, while its later evening price increase demonstrates the importance of managing solar intermittency and storage availability. Data centre developers should compare hourly and long-term delivered electricity costs rather than relying on isolated wholesale price observations. 

Power Availability for Data Center Developers and Grid Infrastructure


Power availability is becoming a big part of choosing where to put a data center in the United States. Even if a place has good land, fiber connectivity, and tax breaks, the project can't go ahead as planned if it doesn't have enough electricity capacity.

Power availability is a crucial aspect in the selection of a US data center. Even with the right location, fiber connection, and tax incentives, a project cannot move forward without adequate electrical capacity and reliable data center power infrastructure such as substations, transmission lines, distribution networks, and backup power systems.

The growing pressure on electricity infrastructure is also reflected in forecasts for national power consumption. Read more about US data center power demand and its expected growth by 2027 to understand how AI expansion is influencing electricity requirements.

ERCOT Power Availability

Texas gets its electricity from various sources, such as nuclear power, natural gas, wind power, and solar power.

The state continues to get investments in hyperscale and AI data centers because it has good energy supplies and room for growth.

However, the number of proposed large-load projects has grown a lot.

ERCOT announced in June 2026 that it received proposals totaling more than 438,000 MW of prospective large-load demand, with data centers making up nearly 89% of the demands. This level of interest underscores the anticipated increase in energy usage and the need for thoughtful grid design, extra generating capacity, and transmission infrastructure to accommodate future data center expansion.

This statistic shows how important it is to plan transmission, make sure projects are qualified, and make accurate predictions of how much energy will be needed.

PJM Power Availability


PJM has a number of established data center markets, including Northern Virginia, Ohio, Pennsylvania, and New Jersey.

The area has a large transmission system and a diversified mix of generation resources. But rising demand from AI and hyperscale facilities is adding further pressure to power resources and grid infrastructure.

According to Reuters' November 17, 2026, report, approximately 20 GW of data center projects entered active development in the PJM region during the first half of 2026, including a planned 10 GW campus in Ohio. The development pipeline highlights the scale of new electricity demand facing PJM and the challenges associated with generation capacity, transmission infrastructure, and large-load integration. 

PJM's July 14, 2026, base residual auction for the 2028/2029 delivery year procured 138,318 MW of unforced capacity, leaving the auction 6,831 MW below the region's reliability requirement. This represents a forward-looking resource adequacy shortfall rather than an existing 6.8 GW interruption in electricity supply. For data center developers, the result highlights the importance of assessing future capacity costs, generation availability, transmission constraints, and the reliability of long-term electricity supply arrangements. 

This means developers must discern between the power capacity that is declared and the power capacity that can actually be provided to a proposed data center site.


Power Availability Comparison

Factor

ERCOT

PJM

Generation Resources

Natural gas, wind, solar, and nuclear

Natural gas, nuclear, coal, hydro, wind, and

solar

Grid Demand

Rapidly increasing large-load demand

Increasing hyperscale and AI electricity

demand

Transmission Constraints

Location-specific constraints and upgrade

requirements

Regional congestion and local transmission

limitations

Power Expansion

New generation, storage, and transmission

investments

Generation development and transmission

expansion

Developer Priority

Confirm grid capacity and interconnection

feasibility

Confirm utility service and available regional

capacity.

ERCOT vs. PJM Interconnection Process


The data center power connections process is a crucial factor in project development schedules, construction planning, and funding.

ERCOT Batch Zero Process

ERCOT established a Batch Zero method to assess major power users who qualify as a group.

It applies to qualified large-load projects of 75 MW and above and is aimed at better assessing the impact of new power demand on system dependability.

Some key considerations include:

  • Assessment of overall electricity use.

  • Evaluation of the requirements for transmission infrastructure.

  • System Impact and Grid Reliability Studies.

  • Project readiness verification.

  • Identifying places that can accommodate more demand for electricity.


ERCOT's Batch Zero framework became effective on July 11, 2026, following approval by the Public Utility Commission of Texas. However, implementation subsequently involved additional verification requirements. On August 3, 2026, the Texas governor directed ERCOT to verify data center projects progressing through the interconnection process. ERCOT subsequently issued conditional classifications and verification requests to developers. 

In an update dated November 5, 2026, ERCOT reported that 257 developers had responded to the first round of verification requests, covering approximately 5,140 questions. A second round of requests was also being issued. Consequently, developers should not assume that entry into Batch Zero automatically guarantees interconnection approval or a confirmed energization date. Site control, financial security, equipment procurement, project documentation, and compliance with eligibility requirements remain important considerations.


PJM Large-Load Integration Process


PJM works with transmission owners and utilities to plan regional transmission and run the energy market.

Large data center projects need to work together with the right provider and follow all PJM and government rules.

PJM announced its proposed fast energization process on Nov. 16, 2026, and filed the proposal with the Federal Energy Regulatory Commission (FERC). The framework seeks to shorten the projected study period for large electricity users and associated generation and transmission services from about two years to one year by coordinating load and generation studies, enhancing project-readiness requirements, and increasing transparency of infrastructure costs. The proposal, though, still must be reviewed and approved by FERC. Developers should thus view the proposed timeline as a policy goal, not as a commitment to interconnection or energization.


ERCOT vs. PJM Interconnection Process Comparison Table

Interconnection Factor

ERCOT

PJM

Large-Load Framework

Batch Zero and related large-load procedures

PJM and utility-led service and transmission

processes

Project Evaluation

Collective assessment of qualifying large loads

Regional and utility-level technical

assessments

Grid Impact

Transmission and reliability assessment

Transmission and system impact assessment

Project Readiness

Documentation and verification requirements

Readiness and service requirements

Recent Development

Batch Zero implementation in 2026

Proposed fast energization process in

November 2026

Developer Focus

Confirm eligibility, deliverable power, and

required upgrades.

Coordinate with utilities, PJM, and relevant

transmission owners.


Renewable Energy and Sustainability Opportunities

Hyperscale cloud providers, colocation operators, and AI infrastructure companies need to think about sustainability more and more.

Both ERCOT and PJM offer renewable energy, but their generation portfolios and regional features differ.

Sustainability Factor

ERCOT

PJM

Wind Energy

Significant wind generation capacity

Regional wind development opportunities

Solar Energy

Strong solar generation potential

Expanding solar projects

Nuclear Energy

Existing nuclear generation

Established nuclear generation fleet

Natural Gas

Major electricity generation source

Major electricity generation source

Battery Storage

Growing investment opportunities

Growing investment opportunities

Renewable PPAs

Wind and solar procurement options

Renewable and nuclear-related procurement

strategies

Sustainability Strategy

Wind, solar and energy storage

Nuclear, renewable energy and long-term

procurement


Many wind and solar energy opportunities exist in Texas. At the same time, PJM gives access to a nuclear power plant fleet that is already up and running, along with growing renewable energy sources.

Access to renewable energy should be considered by data center developers along with hourly electricity demand, contractual agreements, carbon accounting requirements, and the ability to deliver energy.

Developers and operators could also investigate increasing computing efficiency through sustainable compute strategies for US data centers, including hardware optimization, workload management, efficient power utilization, and renewable energy procurement.


Major Data Center Development Locations in ERCOT and PJM

Choosing a location isn't just about how much data center electricity costs. Developers also need to think about the availability of land, fiber connectivity, building costs, the ability to hire workers, tax breaks, and how close they are to customers.

Major ERCOT Data Center Markets

Location

Development Opportunities

Key Advantages

Dallas-Fort Worth, Texas

Hyperscale, colocation, and enterprise data centers

Established telecommunications infrastructure and business ecosystem

Austin, Texas

Technology and cloud infrastructure

Technology industry presence and regional connectivity

Houston, Texas

Large-scale and specialized data center facilities

Industrial and energy sector ecosystem

San Antonio, Texas

Enterprise and colocation facilities

Access to the broader Texas market


Major PJM Data Center Markets

Location

Development Opportunities

Key Advantages

Northern Virginia

Hyperscale and colocation facilities

Established global data center ecosystem

Columbus, Ohio

Large-scale hyperscale development

Regional location and development

opportunities

Pennsylvania

Hyperscale and enterprise facilities

Industrial sites and regional infrastructure

New Jersey

Enterprise and colocation facilities

Proximity to major northeastern business

markets

Maryland


Enterprise and government-related

infrastructure

Access to regional customers and established

infrastructure


Which electricity market is better for data centers?

When comparing ERCOT and PJM for data center developers, there is no clear winner. The best option relies on how much electricity the project needs, where the customers are located, the investment strategy, and the costs of running the business in the long term.

Developer Requirement

Market to Evaluate

Reason

Large-scale campus development

ERCOT

Texas offers substantial land and energy

development opportunities.

Established hyperscale ecosystem

PJM

Strong concentration of existing data center

infrastructure

Access to Northern Virginia customers

PJM

Established connectivity and cloud

infrastructure

Renewable energy procurement

Both

Regional wind, solar and nuclear procurement

opportunities

Competitive retail electricity options

ERCOT

Competitive retail electricity market in many

areas

Access to northeastern enterprise markets

PJM

Established regional infrastructure and

customer concentration

AI and GPU infrastructure

Both

Growing demand for high-density computing

Long-term power security

Both

Requires project-specific supply and grid

planning


Developers should also consider requirements for future expansion. A project that starts with a requirement for 100 MW may ultimately demand several hundred megawatts as more AI compute is added.

Therefore, future electrical capacity assurance should be part of the initial site selection and development strategy.

What Should Developers Evaluate Before Selecting ERCOT or PJM?

Before agreeing to a data center location, developers should do their extensive due diligence in the following areas.

Possible Electrical Capacity: Confirm the actual amount of electricity available for the planned site and the anticipated energization schedule.

Interconnection Requirements: Know the technical studies, project qualifying standards, utility duties, and regulatory approvals.

Overall Electricity Costs: Compare energy costs, capacity-related costs, transmission fees, demand charges, and anticipated market volatility.

Transmission Infrastructure: Identify required substations, transmission upgrades, availability of electrical equipment, and construction timelines. For developers, learning about the top data center equipment suppliers in the US helps them figure out which companies provide important power, cooling, and electrical infrastructure. It is important because the availability of equipment can affect project costs and construction schedules.

Long-term power contracts: Assess power purchase agreements, retail supply contracts, and utility arrangements.

Reliability and Backup Power: Evaluate the needs for battery storage, backup generation, redundancy, and operational continuity.

Development of Future Grid: Track competitive developments, announced power projects, utility investments, and regional transmission expansion plans.

Such considerations can assist developers in reducing project uncertainty, improving investment planning, and locating sites with realistic possibilities for electricity delivery.

Conclusion: 

ERCOT vs. PJM—Selecting the Right Electricity Market for Data Center Development

By comparing ERCOT and PJM, we can see two important power markets that will help the next phase of data center growth in the US.

The competitive electricity market in Texas, its renewable energy supplies, and its growing data center ecosystem all make ERCOT a good place for business growth. But the market needs more large loads, transmission limits are changing, and interconnection needs are also changing, so careful planning is essential.

PJM provides access to established data center markets, large business customers, and a large regional transmission network. At the same time, developers are starting to think about how to deal with grid constraints, rising costs for capacity, and rising demand for electricity.

For investors, developers, and people who run infrastructure, the choice shouldn't just be based on the size of the electricity market or the capacity of a project that has been revealed. Location selection should be based on real power availability, interconnection feasibility, data center electricity costs, transmission infrastructure, and project completion timelines.

Understanding the differences between ERCOT and PJM will continue to be important for data center developers across the United States as AI technology, hyperscale computing, and cloud services grow.

Frequently Asked Questions (FAQs)

What's the most significant difference between PJM and ERCOT?

ERCOT runs an energy-only wholesale electricity market and is in charge of the power grid that serves most of Texas. The PJM is a regional transmission organization that serves 13 states and Washington, D.C. It has markets for both energy and capacity. These differences affect how much energy costs, how power is bought, and how data centers are built.

Which is better for data center builders: ERCOT or PJM?

There are chances to grow in both areas. Texas's competitive electricity market, renewable energy supplies, and open land all make ERCOT appealing to developers. PJM gives you access to well-known data center hubs in places like Ohio, Pennsylvania, and Northern Virginia. Which option is best relies on how much electricity costs, how much power is available, and the needs of the project.

How are the prices for electricity different between PJM and ERCOT?

PJM runs both energy and capacity markets, while ERCOT only runs an energy-only wholesale market. The price of electricity in both areas is based on wholesale prices, transmission costs, utility rates, and deals for buying power. Before choosing a market, developers should look at how much electricity costs in that area.

Where do the biggest problems lie in ERCOT and PJM's data center power infrastructure?

Transmission capacity, grid congestion, energy supply, and rising demand from AI and hyperscale data centers are all problems that both markets have to deal with. To make sure that electricity gets to people when they need it, developers have to look at substations, transmission lines, power distribution networks, and backup power systems.

What should builders think about before deciding whether to build a data center with ERCOT or PJM?

Developers should look at the amount of electricity that is available, how long it takes to connect to other power grids, how much electricity costs, the availability of land, fiber connections, and long-term power agreements. When choosing a location, you should also think about how much room you will need for future growth and how reliable the grid is.