Loudoun County Supervisors Pause Data Center Applications for up to 12 Months
A majority of the Loudoun County Board of Supervisors voted at its November 17, 2026, meeting to defer final votes on legislative data center and electrical substation applications for up to 12 months, the maximum period permitted under Virginia law.
Final Decisions Postponed Under New Resolution
The Board made the deferral retroactively effective as of September 15. Under the terms of the adopted resolution, the pause could affect 33 legislative applications currently active in the county.
The deferral stops short of a full moratorium. A previous legal opinion from the Loudoun County Attorney concluded that a moratorium halting all data center approvals would not be legal.
The Board's action instead delays final votes while allowing the application process itself to continue.
Policy Review Drives the Timeline
The Board's stated purpose for the pause is to give the county time to finish its review of current data center policies and regulations.
That work is underway through the Data Center Standards and Locations project, which proposes amendments to the Loudoun County 2019 Comprehensive Plan and the Loudoun County Zoning Ordinance concerning data center standards and locations.
Because those amendments could affect both existing and new legislative applications, the Board intends for the pause to end when it adopts the amendments. The project is expected to conclude in the summer of 2027.
How Applications Proceed During the Deferral
Developers remain free to submit applications proposing or allowing data center and substation uses during the pause. County staff will continue reviewing submissions and scheduling the Planning Commission's public hearing.
However, the Board's intent is to hold off on Board of Supervisors public hearings and final votes until the Data Center Standards and Locations project is finished.
The pause will not cause any applications to become inactive.
Virginia law requires action on legislative applications within one year, a period that begins when applications are first submitted to the Planning Commission.
The Board may consider exceptions to the pause for applications involving electric grid reliability or those whose statutory decision period is about to expire.
Limits on the Pause's Reach
The deferral does not apply to legislative applications for properties located within the Route 28 Tax District. It also does not affect applications subject to administrative processes, leaving those to proceed under existing procedures.
Earlier Shift in County Oversight
The pause builds on an earlier Board decision ending by-right data center development in Loudoun County. Under that action, every data center project must come before the Board for a vote through the county's special exception process, meaning no proposal can move forward without direct Board consideration.