Core Scientific Files $1.3 Billion Buildout for 285 MW Hunt County Data Center Campus
Core Scientific has taken a formal step toward building out its Hunt County data center campus, filing plans with the Texas Department of Licensing and Regulation for a development that the company values at USD 1.3 billion.
Details
The submission, made under the name Telios Quinlan One, LLC, covers the Core Scientific Hunt data center project at 4852 County Road 3507 in Quinlan, approximately 53 miles northeast of Dallas.
The filing describes a data center core and shell building of 341,325 sq ft (31,710 sqm), with construction scheduled to begin in November 2026 and finish in September 2028. The land, which is currently mostly vacant, sits near Acciona Energia's 190MW Cunningham battery energy storage system.
Ownership and capacity outlook
The Quinlan site entered Core Scientific's portfolio in March, when the company announced it had purchased Telios Quinlan One LLC for USD 232.5 million, securing a 265-acre tract in Hunt County.
At the time of the acquisition, Core Scientific outlined plans for a campus with up to 285MW of leasable capacity, corresponding to 430 MW of gross capacity spread across multiple buildings. An on-site substation is planned, with the company targeting an initial energization in 2027 and full power delivery by 2029.
AMD commitment anchors the campus
A significant portion of the planned capacity is already earmarked for a single tenant.
Under a broader leasing agreement between the two companies, AMD is set to take 110MW at the Hunt County site. That commitment represents a substantial share of the campus's 285 MW of leasable capacity, with Core Scientific leasing approximately half of the site to the chipmaker.
Local context in Quinlan
The Hunt County project is not the first large-scale energy or infrastructure proposal to surface in Quinlan. Renewable energy infrastructure developer Belltown Power had previously pursued a project in the area but withdrew its application earlier this year, according to a local group that opposes data center development.
A company reshaping itself around AI
Core Scientific, founded in 2017, originally operated as a cryptomining data center provider but has since redirected its business toward AI data center development.
Its facility footprint spans Alabama, Georgia, Kentucky, North Carolina, North Dakota, Oklahoma, and Texas.
CoreWeave, an AI cloud firm, is among its major customers alongside AMD. The company signaled an acceleration of that shift this week, announcing its intention to fully exit the Bitcoin mining business by the end of the year as it concentrates on AI infrastructure.
The Hunt County filing adds to that strategy, positioning Core Scientific to deliver new capacity dedicated to AI workloads in the Dallas-Fort Worth region.