Behind-the-meter power for data centers advanced in Ohio on Nov. 19, 2026, when the Ohio Power Siting Board (OPSB) approved a pair of natural gas-fired electric generation facilities in Fairfield and Pickaway counties.

Details

Neither plant will be connected to the electric power grid. Each will instead operate adjacent to, and supply power directly to, a neighboring data center.

The decisions were announced from Columbus and clear the way for the projects to proceed under a set of conditions the board adopted in each case.

The board's authority in the two cases extends only to the generation facilities themselves; it has no jurisdiction over approval of the data centers.

Ashville Energy Center Approved With 41 Conditions

PowerConneX, Inc. received approval to construct and operate the 800 MW Ashville Energy Center on 110 acres in the Village of Ashville, Pickaway County.

The project site sits along State Route 752, east of State Route 23. In its approval, the OPSB adopted and modified an agreement between PowerConneX, the Village of Ashville, and the OPSB staff.

Under that agreement, PowerConneX must adhere to 41 conditions designed to minimize potential impacts during construction and operation of the facility.

The agreement also obligates PowerConneX to honor the financial commitments it has made to the Ashville community.

Millersport Project Pairs Gas Plant With Battery Storage

Fairfield Energy Center, LLC received approval to construct and operate a 1,350 MW generation facility along with a 1,040 MW battery energy storage facility.

The project will occupy 122 acres in the Village of Millersport, Walnut Township, in Fairfield County, near the intersection of State Route 37 and State Route 204.

In approving the project, the OPSB adopted an agreement between Fairfield Energy Center and the OPSB staff. The agreement requires Fairfield Energy Center to adhere to 36 conditions designed to minimize potential impacts during construction and operation of the facility.