TeraWulf Erects Structural Steel at 480 MW Kentucky AI Campus for Anthropic
Steel is rising at TeraWulf's Justified Data Campus in Hawesville, Kentucky, where the data center developer has shifted from foundational work to vertical construction on a 480MW facility purpose-built for artificial intelligence company Anthropic.
Progress Announced
The company announced the progress on LinkedIn, noting that the first structural steel is going up at the Hancock County site.
The majority of structural steel for the first building, known as CB-1, has already been delivered and staged, with substantial deliveries also completed for CB-2.
TeraWulf described the development as an important transition as it advances large-scale infrastructure built specifically for its customer Anthropic.
Fluor Expands EPC Partnership
Engineering, procurement, and construction work at the site is being handled by Fluor Corporation, a partnership that has grown beyond the two companies' earlier collaborations. Leo Kaid, president of Fluor's advanced technologies and life sciences business line, commented on the arrangement earlier this month.
Fluor is proud to expand its partnership with TeraWulf and support the delivery of infrastructure needed to meet rapidly growing demand for artificial intelligence and high-performance computing, Kaid said.
He added that the company's integrated engineering, procurement and construction capabilities, combined with its data center expertise and skilled workforce, position it to deliver the project with a strong focus on safety, quality and schedule certainty.
Former Century Aluminum Site Transformed
The Justified Data Campus occupies a 790-acre site in Hancock County that was previously used for aluminum processing. Century Aluminum operated at the location from 1969 until 2022, and TeraWulf acquired the property with plans to convert the long-standing industrial site into digital infrastructure.
The project was announced in February, and the first facility at the campus is due to come online in 2027.
Anthropic will lease capacity at the site, with Google acting as a backstop for the arrangement. The campus is designed to support large-scale AI and high-performance computing workloads.
Growing Portfolio Beyond Kentucky
The Hawesville development is one of several projects in TeraWulf's expanding portfolio. The company currently operates a campus outside Buffalo, New York, located at a former coal power plant.
TeraWulf initially mined cryptocurrency at that 180-acre site before beginning to pivot the campus toward AI and HPC uses.
Core42 and Fluidstack are live customers at the New York location. In addition to its operating site and the Hawesville campus, TeraWulf is developing sites in Maryland and Kentucky and is planning a second development in Lansing, New York.
The move away from cryptocurrency mining toward AI and HPC infrastructure reflects a broader strategic direction for the company, and at 480 MW of capacity, the Hawesville campus represents one of its largest commitments to date.
Steel Deliveries Position Project for Next Phase
With the majority of structural steel for CB-1 staged and substantial deliveries for CB-2 complete, the project is positioned for continued above-ground construction activity in the coming months.
The first facility is expected to come online in 2027, transforming a site with more than five decades of aluminum processing history into a modern AI infrastructure hub serving one of the leading companies in artificial intelligence.