Vantage Drops Trident Data Center Site Near Green Valley Ranch After Aurora Protests
Aurora City Attorney Pete Schulte told the city council on Monday night that Vantage Data Centers will not build its proposed Trident Data Center at the site originally proposed near several Green Valley Ranch neighborhoods. The announcement drew standing applause from the crowd attending the meeting.
Company Statement
The company later confirmed the decision in its own statement to 9News, The Gazette's news partner. The company said it "remains committed to being a responsible long-term partner in the state." Spokespeople told 9News that Vantage is still searching for an alternative location.
Decision Landed Just Before Council Was Set to Act
The withdrawal came as the council prepared to take up a resolution urging the company to move the data center elsewhere.
The council planned to consider passing that resolution, and Vantage's announcement arrived shortly before that consideration.
Monday's decision followed months of protest and debate over the proposed location. The September community meeting in Green Valley Ranch, attended by about 100 area residents and addressed by community leader Tara Miller, took place as opposition to the proposed site organized.
October Letter Had Already Committed Company to Looking Elsewhere
The Monday announcement was not the company's first signal that it would look beyond the original site. In late October, Vantage officially agreed in a letter to the council to seek alternative locations for the proposed data center.
In that letter, Vantage officials asked the council for at least 90 days to find another location and requested that the city hold off on new data center rules until then.
Both the council's planned resolution and the company's request regarding new rules were pending as of Monday night's meeting, where the site decision was announced.
Company Statement Stops Short of Leaving Colorado
In its statement to 9News, Vantage characterized the decision as limited to the current site rather than a departure from the state.
Allen's statement said the company will no longer pursue the current site for the proposed campus while remaining committed to the state as a long-term partner.
Spokespeople confirmed to 9News that the search for an alternative location continues.
The announcement was made publicly by the city attorney rather than by the company directly, with Vantage's own statement subsequently provided to 9News.
What Was Proposed at Green Valley Ranch
The Trident Data Center was proposed near several Green Valley Ranch neighborhoods, a location that drew months of protest and debate before Monday's announcement.
The September 22, 2026, community meeting, where Miller spoke to about 100 area residents, was part of the organizing against the proposed location.
As of Monday night, Vantage had not identified a replacement site, and the council had not acted on the resolution it had planned to consider.
The company's request that the city hold off on new data center rules during its search was also still pending when the site decision was announced at the meeting.